MArina Infrastructure





Lake View Gallery
 

 

Lake View Progress for February 2012

electrical metal boxes
external plaster
front view
internal plaster
masonary in progress
passage masonary
reinforcement at fourth floor level
 

 

Lake View Progress for January 2012

column boxes
DB
puttied walls
safety

 

Lake View Progress for December 2011

decking for 3rd slab in progress
electrical conduiting
front view
masonary in progress
plastering in progress
putty works
rear view
retaining wall another view
retaining wall
sand washing plant

Lake View Progress for November 2011

2nd floor level
central staircase
chasing for electrical works
columns at third floor level
front entrance
Internal masonary & door frames
masonary at Ground & first floor levels
mesh fixing at concrete & masonary joints
rear view
ventilators in position

 

Lake View Progress for October 2011

Masonary in Progress
Concreted Slab
Rear Elevation
Reinforcement in Position

 

Lake View Progress for October 2011

Masonary in Progress
Concreted Slab
Rear Elevation
Reinforcement in Position

 

Study of Drawings
Columns at Ground Level
   

 

 

Lake View Progress for September 2011

slab shuttering at 2nd floor level
Reinforcement in Stock
Reinforcement in Readiness
Reinforcement at 2 floor level

 

Front View
     

 

 

Lake View Progress for August 2011

Bar bending
Concreting 2 slab
Concreting another view
Ready mix concrete

 

Reinforcement in position for slab
Reinforcement in position for slab
   

 

 

Lake View Progress for July 2011

Columns from GF to FF
Columns GF Slab to FF slab
Front view GF slab
Parking bay columns

 

Shuttering for 2nd part of GF slab
Shutttering for 2nd part of slab
Slab casted
 

 

Lake View Progress for June 2011

Columns for 1st slab
Dewatering process
Foundation works
Plinth beams

Lake View Progress for May 2011

Columns for 1st slab
Dewatering process
Foundation works
Plinth beams
Plywood for shuttering
     
Lake View Progress for April 2011
View excavated area
Backfilling in progress
Barbending works in progress
Boulders in stock for boulder packing below foundations
Completed raft footing with pedestals
Excavation & foundations in progress
Excavation work & mobilization
Excavation work for foundations