| Sri Lakshmi Residency Progress for March 2012 |
Solar Panels |
harware for doors |
balcony doors |
internal painting in progress |
Close Up |
Front Elevation |
north elevation |
close up |
south elevation |
terrace flooring |
|
|
| Sri Lakshmi Residency Progress for February 2012 |
wall tiling |
main door |
earthing pits |
lift shaft |
east elevation |
compound wall |
side elevation |
front elevation |
roof sheeting |
|
|
|
| Sri Lakshmi Residency Progress for January 2012 |
bathroom tiling |
passage tiles in stock |
south retaining wall |
rear elevation |
retaining wall north side |
compound wall on north road |
north road extension |
north elevation |
front elevation |
south elevation from kadri road |
truss works in terrace |
|
| Sri Lakshmi Residency Progress for December 2011 |
Door cum window frame |
Elevational grooves |
French door frame |
Front elevation |
Kitchen platform & tiling |
Putttied walls |
Quality checks |
South elevation |
Truss works in progress |
Windows & grill works |
|
|
| Sri Lakshmi Residency Progress for November 2011 |
Bedrooms |
Front elevation |
kitchen platform with dado |
Main door |
retaining wall north sidel |
South elevation |
Truss fabrication in progress |
Ventilators in position |
| Sri Lakshmi Residency Progress for October 2011 |
RR Masonary North Wall |
north elevation |
Kitchen |
front elevation |
French doors for Balcony |
External Plaster |
Dining Wash Basin |
Balcony Railing |
south elevation |
|
|
|
Sri Lakshmi Residency Progress for September 2011 |
balcony flooring & tiling |
window shutters |
west elevation |
toilet tiling |
protection to flooring |
passage plastering |
parapet plastering |
north elevation |
kitchen tiling |
kitchen racks |
door frames |
door cum window |
balcony french doors |
|
|
|
| |
| Sri Lakshmi Residency Progress for August 2011 |
Dining sink |
East elevation |
Masonary lineout at 6th floorr |
Model flat flooring |
North elevation |
Quality checks for wall painting |
South elevation |
Switch boxes |
Terrece parapet wall |
Toilet plumbing |
View of balcony frame |
View of bedroom window |
| |
| Sri Lakshmi Residency Progress for July 2011 |
Puttywork for walls |
Rear elevation |
Ceiling plaster |
Conduiting in progress |
Door frame fixing |
Front elevation |
Metal lintels |
Plastering for walls |
| Sri Lakshmi Residency Progress for June 2011 |
concrete frames for toilets |
electrical boxes |
internal partition walls |
Internal plaster |
Masonary works |
Mesh works |
Rear view |
Rear view-terrace slab |
Safety precautions |
Side elevation |
Wooden frames |
|
Sri Lakshmi Residency Progress for May 2011 |
view-masonary |
Columns casted at 5th floor |
Decking for 5th slab |
Front elevation |
Masonary in progress |
Partition walls |
North elevation |
|
| Sri Lakshmi Residency Progress for April 2011 |
3rd slab reinforcement |
Columns for 5th slab |
Front elevation |
Masonary in progress at first & ground floor |
Masonary works in completion for ground floor |
Material in stock for masonary |
North elevation |
Packing between masonary & beams |
partition walls |
Slab reinforcement for 4th slab |
Staircase shuttering |
|
| Sri Lakshmi Residency Progress for March 2011 |
Column concreting |
Decking for 2 floor slab |
Decking for 2nd slab another view |
decking for 3rd floor slab |
North elevation |
North west elevation |
| Sri Lakshmi Residency Progress for February 2011 |
2nd floor slab 1st phase |
Columns for First floor slab phase 2 |
Curing for columns |
Curing works |
Reinforcement works |
Side view |
Sri Lakshmi Residency Progress for January 2011
|
Decking for G slab |
Decking system for 1st floor slab |
front view |
Lift wall concreted for lift no 2 |
Plinth beams |
plinth beams concreted |
Reinforcement |
Reinforcement works |
Slab shuttering |
View of 1st slab |
|
|