MArina Infrastructure





Iris Project Gallery
 
Iris Progress for August 2011
Aluminium works
Basement concrete
Car park concrete
Corridor lighting
Aluminum work
Duct lines
Duct paintings
False ceiling in toilets
Kitchen platform with tiling
Lift installation
Main door polish
Panel room
Plumbing lines in terrace
Sanitary ware
Side and front view
Side elevation
Switches
Toilet dado
View of corridor
 
Iris Progress for July 2011
Basement ceiling painting
Basement ceiling plaster
Beautification works
Corridor putty works
Corridor tiling
Duct painting
Elevation -closeup front & side
Granite platform
Hardware for doors
Internal painting
Kitchen grill fixing
Main door -teak veenered
Side elevation
Staircase railing
 

 

Iris Progress for June 2011

balcony railing
basement plastering
bedroom window
Carpentry work
Compound wall
Duct plastering
Elevation close up view
External paint primer
Granite paltform with sink
Granite platform
Painting works
Puttied wall surface
Side elevation
Terrace floor
Window railings

 

Iris Progress for May 2011

Balcony railing
Brick cladding for elevation
Ceiling putty work
Compound wall
Elevation beautification
External painting
External plastering
flooring
Iris front view
Internal putty work
Kitchen platform & flooring
Roof sheeting with skylite
Side elevation
Terrace sheeting works
Iris Progress for April 2011
View roof sheeting
Close up eastern view
Completed roof sheeting
corridor & duct plaster
Work In Progress
Work In Progress
Work In Progress
Work In Progress
East elevation
Eastern view
External plaster in progress
Front view
External plaster with elevational
featuresMain door frames in position
Roof sheeting profile
skylite
solar panels in position
Solar panels
solar tanks
tiling in progress
western elevation
Iris Progress for March 2011
View truss works
Balcony grill fixing
Bedroom windows with grills
Curved truss
Duct plaster
East elevation
External plastering south side
Grills for windows
Kitchen platform with grills
Lift machine room and water tank plaster
Main door BST shutter
North East elevation
Passage ceiling plaster
Passage plaster
Plastering in progress
Puttied internal walls
Puttied walls
Sand seiving
Tiling in kitchens
Tiling work in progress
Toilet tiling
Side elevation
Truss works
Western elevation ext plaster
Iris Progress for Febraury 2011
Ceiling plaster in corridors
Chasing work for electrical conduits
Front elevation
Grills for windows
Grills painting
Internal plastering for walls
Kitchen grills
Living room
Masonary for ducts at terrace
Puutied walls for sample flat
Roof Truss works
Sand cleaning operation
Sand seiving machine
Side elevation
Tiles stock
Tiling for sample flat
Iris Progress for Janaury 2011
Safety precautions
Plastering mesh work
Metal boxes
Mesh work between different materials
Lintels in position
Decking for terrace slab
Lintels in position
Latrite masonary work
conduits
concreting terrace slab
Blockwork